Industrial facilities: What role does the construction phase play in the approval procedure?

VwGH Ra 2023/04/0262 to 0266-16 | 01.09.2026

The Austrian Supreme Administrative Court (VwGH) had to determine whether emissions must already be considered during the trade law approval procedure for industrial facilities. The case concerned impacts arising during the construction of a commercial facility.

In the case at hand, the expansion of a production site through the addition of another plant was approved. The neighbouring property owners raised objections, particularly regarding noise and dust emissions. These were expected to result from extensive excavation works, construction site installations and temporary material storage. The Administrative Court of the Province of Salzburg, however, took the view that such impacts did not fall within the scope of the trade law approval procedure for industrial facilities.

The VwGH rejected this legal interpretation. The assessment must not be limited to the impacts of subsequent operations. Emissions arising during the construction of the facility must also be examined (Section 74(2) of the Austrian Trade, Commerce and Industry Regulation Act 1994). Neighbours may already raise objections concerning impacts caused by construction works during the trade law approval procedure for industrial facilities (Section 75(2) of the Austrian Trade, Commerce and Industry Regulation Act 1994).

As the Administrative Court had failed to adequately examine these impacts, the VwGH quashed its judgment.